JWST news
by John Hutchings and
Rene Doyon |
 |
In May this year, NASA announced a delay of 1 year in the
launch date, from June 2013 to June 2014. This was anticipated, as delays have
accumulated in delivery of essential electronic components, and scheduled
testing time, to where the mandatory contingency time no longer covered them.
The total cost impact is almost all in the extra year of keeping the team
working. On the Canadian side, our instrument delivery times are not changed,
and we are keeping to our schedule, while dealing with the usual problems and
worries that occur in space instrumentation. All the instruments are now past
critical design review and are producing actual hardware. The overall
performance of the telescope still looks as-designed, but receives constant
attention from the Science Working Group. One positive result of the delay is
that there is an extra year to prepare for operations. In response to the time
and budget squeeze on operations support at STScI, we have recruited two extra
Canadian scientists to Baltimore to support our instrument. The Canadian team
of four now consists of Alex Fullerton and Pierre Chayer, who have been in
place for a couple of years, joined this April by Kevin Volk and Andre Martel.
The project-wide bi-annual Partners Workshop was hosted by CSA in May, at the
Chateau Laurier in Ottawa, and welcomed by CSA president Steve Maclean. At
this occasion, CSA unveiled the official logo for the project, which is at the
top of this report.
The pictures show our FGS engineering model instrument
which has been in test in the cryogenic vacuum facility of CSA’s David Florida
Lab in Ottawa. Flight detectors, optics, filters, and etalon are in various
stages of fabrication and test. The other JWST instruments are in similar
stages, and the telescope beryllium primary mirror segments are all in process,
with the first few closing in on specified performance as they enter the final
touch-up polishing. The all-essential sunshade and deployment are in final
design, with extensive testing planned on a 1/3 model now under construction.